Wednesday, March 22, 2006

More work was done preparing the base of the cellar hole for the pouring of the footings on Thursday. Joe D built up a 3' base of 6" stone and then topped it off with smaller gravel.




The leach field is almost filled with sewer gravel and the area in front of the foundation is starting to approach finish grade.

Leach Field