Wednesday, November 22, 2006

The guys from T&J were in this week installing the Furnace and piping in the utility room. The white unit is the Buderus furnace. Seems kind of small for a furnace, but they tell me it will heat the house just fine.

Sunday, November 19, 2006

Kyle worked this week on the second floor electric. He livened up a few circuits off of the generator. It was a busy weekend, Russ, Linda and Nicole stopped by on Saturday and Russ ended up staying and helping with the blocking for future paneling. Dad was the Cut Man and Russ was nailed the pieces in.
On Sunday Phil stopped by in the AM and installed all the in wall wiring for the alarm. Dunc and Dad stopped by in the afternoon to continue working on the wall blocking. Joe D left his Loader backhoe at the lot so Dad and Joe could move some of the fill back to behind the garage.

Friday, November 03, 2006

The posts for the back decks have been poured. The ones off the kitchen still need to be taller and that is why they have rebar sticking out of them. Once they are backfilled we will add on more sonotubes and pour them higher.

The Gas meter was installed - We are getting closere to having heat.

Thursday, November 02, 2006

The last couple have weeks have been fillled with additional sitework, the Gasline installation by NStar, and the start of the back decks (footings).

Cement being poured for the the back deck footings.
Lots of additional fill have been dropped on the lot as we try to get to final grade. We have been fortunate to get fill from a town project.
The Gas line was installed earlier this week. We are now just waiting for the Meter. Electricity is the remaining missing utility.