West Elm St Home
New Address: 72 West Elm St Hopkinton MA 01748 PH: Remains the same 497-0732
Blog Archive
►
2012
(1)
►
December
(1)
►
2010
(1)
►
June
(1)
►
2009
(11)
►
November
(1)
►
October
(2)
►
August
(1)
►
July
(1)
►
June
(1)
►
May
(2)
►
April
(3)
►
2008
(14)
►
November
(2)
►
October
(2)
►
June
(2)
►
May
(1)
►
April
(1)
►
March
(1)
►
February
(2)
►
January
(3)
►
2007
(36)
►
December
(3)
►
November
(7)
►
October
(3)
►
September
(1)
►
August
(6)
►
July
(3)
►
June
(5)
►
May
(3)
►
March
(2)
►
February
(2)
►
January
(1)
▼
2006
(70)
►
December
(2)
►
November
(4)
►
October
(1)
►
September
(4)
▼
August
(11)
More Trim and Siding work today and yesterday. Th...
Kevin's guys have been primarily doing exterior tr...
Monday, Tuesday, & Wednesday the Mason's finished...
Today was a day for Fill and Masonry: We brought i...
More work on the fireplaces and Chimney. We cont...
Today we had a visit from a turkey at the house. ...
On Monday the Kolbe windows and doors were deliver...
Today the Roofer finished almost all of the roof. ...
Today the framing crew worked on the roof of the F...
Weekend Update:Friday the Framing Crew finished th...
Joe got his new Tub Today!!!Because of the Heat t...
►
July
(19)
►
June
(6)
►
May
(3)
►
April
(3)
►
March
(15)
►
February
(2)
►
2005
(1)
►
October
(1)
About Me
Michael
View my complete profile
Thursday, August 31, 2006
More Trim and Siding work today and yesterday. They also installed the Ribbon Joist for the Decks so the sidwallers can side around them.