Alot of work was done on the 2nd Floor Framing today. They also installed both sets of Stairs. The picture below is taken from me standing on the outside edge of the garage looking back at the house:
This is the opposite picture looking back from over the toy room back towards the garage:
The picture below is of the kids bedrooms and bath:
Here are the main stairs for the house:
Here are the back stairs:
The front room will cantilever out into the roof of the front porch:
The garage is starting to take shape:
The framers were able to move the concrete cutouts so they don't get in the way of the cement floor guys who are expected next week:
We were fortunate to receive some free fill from a local person who is having an inground pool installed. We need about 10 more pools to get us close to where we need to be for fill: